chore: remove phase 11 (Platform Adaptation)
This commit is contained in:
@@ -134,36 +134,3 @@ Plans:
|
||||
Plans:
|
||||
- [x] 10-01: ProxyPool 核心类实现 — 从 YAML/环境变量加载代理,Round-Robin 轮换
|
||||
- [ ] 10-02: 健康检查与 ZhihuCrawler 集成 — 被动检测、冷却恢复、代理切换
|
||||
|
||||
#### Phase 11: Platform Adaptation (平台适配)
|
||||
**Goal**: 针对知乎和 B 站的反爬策略进行专项优化,整合前面所有反爬能力
|
||||
**Depends on**: Phase 11
|
||||
**Requirements**: PLAT-01, PLAT-02
|
||||
**Success Criteria** (what must be TRUE):
|
||||
1. 知乎爬取针对登录态检测和请求频率限制进行了优化
|
||||
2. B 站爬取针对视频/专栏元数据获取进行了优化
|
||||
3. 两个平台的爬取成功率相比 v1.2 有明显提升
|
||||
**Plans**: TBD
|
||||
|
||||
Plans:
|
||||
- [ ] 11-01: 知乎反爬适配 (PLAT-01)
|
||||
- [ ] 11-02: B 站反爬适配 (PLAT-02)
|
||||
|
||||
## Progress
|
||||
|
||||
**Execution Order:**
|
||||
Phases execute in numeric order: 1 → ... → 9 → 10 → 11 → 12 → 13 → 14
|
||||
|
||||
| Phase | Milestone | Plans Complete | Status | Completed |
|
||||
|-------|-----------|----------------|--------|-----------|
|
||||
| 1. Foundation | v1.0 | 3/3 | Complete | 2011-03-15 |
|
||||
| 2. Adapters | v1.0 | 2/2 | Complete | 2011-03-15 |
|
||||
| 3. Processors | v1.0 | 3/3 | Complete | 2011-03-15 |
|
||||
| 4. Pipeline | v1.0 | 2/2 | Complete | 2011-03-15 |
|
||||
| 5. 归档与目录优化 | v1.1 | 3/3 | Complete | 2011-03-16 |
|
||||
| 6. 代码整合 | v1.1 | 3/3 | Complete | 2011-03-16 |
|
||||
| 7. 登录认证体系 | v1.2 | 3/3 | Complete | 2011-03-17 |
|
||||
| 8. 内容爬取实现 | v1.2 | 3/3 | Complete | 2011-03-17 |
|
||||
| 9. Pipeline 整合 | v1.2 | 1/1 | Complete | 2011-03-17 |
|
||||
| 10. Proxy Pool | 2/2 | Complete | 2011-03-18 | - |
|
||||
| 11. Platform Adaptation | v1.3 | 0/2 | Not started | - |
|
||||
|
||||
+3
-3
@@ -4,10 +4,10 @@ milestone: v1.3
|
||||
milestone_name: Anti-Crawler Optimization
|
||||
status: executing
|
||||
stopped_at: Completed 10-02-PLAN.md
|
||||
last_updated: "2026-03-18T14:35:35.015Z"
|
||||
last_updated: "2026-03-18T14:38:49.662Z"
|
||||
last_activity: 2026-03-18 — 10-01 proxy pool core complete
|
||||
progress:
|
||||
total_phases: 11
|
||||
total_phases: 10
|
||||
completed_phases: 9
|
||||
total_plans: 29
|
||||
completed_plans: 28
|
||||
@@ -25,7 +25,7 @@ See: .planning/PROJECT.md (updated 2026-03-18)
|
||||
|
||||
## Current Position
|
||||
|
||||
Phase: 10 of 11 (Proxy Pool)
|
||||
Phase: 10 of 10 (Proxy Pool)
|
||||
Plan: 1 of 2 in current phase
|
||||
Status: In progress
|
||||
Last activity: 2026-03-18 — 10-01 proxy pool core complete
|
||||
|
||||