- Archive roadmap to milestones/v1.5-ROADMAP.md - Archive requirements to milestones/v1.5-REQUIREMENTS.md - Update ROADMAP.md with collapsed v1.5 entry - Update PROJECT.md with validated requirements - Add semantic segmentation to backlog Delivered: B站视频简化处理流程 Co-Authored-By: Claude Opus 4.6 <noreply@anthropic.com>
70 lines
1.8 KiB
Markdown
70 lines
1.8 KiB
Markdown
---
|
|
gsd_state_version: 1.0
|
|
milestone: v1.4
|
|
milestone_name: Zhihu Anti-Crawler
|
|
status: completed
|
|
stopped_at: Completed 12-02 Pipeline Integration
|
|
last_updated: "2026-03-21T15:24:05.123Z"
|
|
last_activity: 2026-03-19 — Completed 12-02 Pipeline Integration
|
|
progress:
|
|
total_phases: 12
|
|
completed_phases: 10
|
|
total_plans: 31
|
|
completed_plans: 30
|
|
percent: 100
|
|
---
|
|
|
|
# Project State
|
|
|
|
## Project Reference
|
|
|
|
See: .planning/PROJECT.md (updated 2026-03-19)
|
|
|
|
**Core value:** 可靠、可维护的处理管道 - 每个步骤独立、可验证、可恢复
|
|
**Current focus:** Phase 12 - SRT 简化处理器 (完成)
|
|
|
|
## Current Position
|
|
|
|
Phase: 12-srt-simplifier (2/2 plans complete)
|
|
Plan: 12-02 (完成)
|
|
Status: Phase 12 Complete
|
|
Last activity: 2026-03-19 — Completed 12-02 Pipeline Integration
|
|
|
|
Progress: [██████████] 100%
|
|
|
|
## Accumulated Context
|
|
|
|
### Decisions
|
|
|
|
Key decisions from v1.0-v1.4 (preserved):
|
|
- 管道模型 — BaseProcessor + Pipeline 架构
|
|
- 步骤级状态 — WorkflowStateManager
|
|
- Schema 验证 — Pydantic v2
|
|
- 顺序执行 — 简单性和可调试性
|
|
- CLI subparsers — 可扩展命令结构
|
|
|
|
v1.5 scope:
|
|
- 仅针对 B 站视频处理
|
|
- 简化流程:SRT → 去时间戳 → 分段 → 纠正 → Markdown
|
|
- 移除深度观点分析
|
|
|
|
v1.5 Phase 12 decisions:
|
|
- TDD approach with RED-GREEN cycles for all modules
|
|
- Lazy import for ASRCorrector to avoid dependency issues
|
|
- Simple rule-based segmentation (no LLM) for speed
|
|
- ASR correction is optional, fallback to original text
|
|
- B站视频使用 SRTProcessor,其他平台保持 AnalyzeProcessor
|
|
- Pipeline 平台路由:检测 platform=bilibili + content_type=video
|
|
|
|
### Blockers/Concerns
|
|
|
|
None.
|
|
|
|
## Session Continuity
|
|
|
|
Last session: 2026-03-19
|
|
Stopped at: Completed 12-02 Pipeline Integration
|
|
Resume file: None
|
|
|
|
**Next step:** Phase 12 完成,可以继续下一里程碑任务
|